Houston SWPPP requirements (2026)

Houston wants a copy of your NOI or notice at least 2 days before earth work.

Check your site free

Free. No account, no email.

Key takeaways

TCEQ's permit applies in Houston, and the city treats it as the floor. Check the state rules first in do I need a SWPPP.

What did we verify for Houston?

TopicWhat the city's page says
Copy to the city"You must notify the City of Houston with a copy of your NOI ... or a copy of your CSN ... at least two (2) days prior to any earth disturbing activities"
Permit and plan reviewThe city does not issue this permit. Plan review: not required. Re-inspection fee: $109.46
InspectionsAll construction sites within city limits will be inspected, unannounced. Enforcement actions may be taken
Post-constructionA separate Storm Water Quality permit for new and redevelopment asks for a signed and sealed plan cover page
Grading and fillA building-permit application plus Form CE-1094. Fill over 1 foot at the property line needs a Texas engineer's retaining wall design

What is Harris County's role?

In unincorporated areas, county inspectors enforce the TCEQ permit and the Harris County Stormwater Quality Management Regulations.

The county's Stormwater Quality permit is issued as part of the Civil Development Plan Review and renewed yearly after a Certificate of Compliance.

What should I check with the city?

FAQ

Do I send the city a copy of my small-site notice?

Yes. The city page asks for a copy of the NOI or the Construction Site Notice at least 2 days before earth disturbing activities.

Does Houston issue my stormwater permit?

No. TCEQ's permit is the construction permit. The city says it does not issue it.