Final stabilization at 70% in Texas (2026)

Final stabilization means perennial cover at 70% of native vegetation, or permanent measures like riprap.

Check your site free

Free. No account, no email.

Key takeaways

What is the difference between temporary and final stabilization?

TemporaryFinal
What it isExposed soil gets a protective cover or structural control that prevents pollutants from moving, such as seeding, geotextiles or mulchesAll soil disturbance is done, and unpaved areas have uniform perennial vegetation at 70% of the native background density, or equal permanent measures such as riprap or gabions
Percent coverThe permit gives noneAt least 70% of native background cover

What are the deadlines?

When work stops permanently, or stops temporarily for more than 14 calendar days, start stabilizing as soon as practicable, no later than the end of the next work day.

Finish stabilizing within 14 calendar days of starting.

The permit allows exceptions to these deadlines for frozen ground, arid or drought-stricken areas, places where even non-vegetative cover is infeasible (use temporary perimeter controls and write down why) and circumstances beyond your control.

The 14-day trigger applies once it is known with reasonable certainty that work will stop for 14 or more days.

Are there special cases?

What happens after final stabilization?

A small site removes its notice and sends a copy to the storm sewer operator within 30 days. A large site files a Notice of Termination online within 30 days.

See small-site closeout.

FAQ

What does 70% mean?

Uniform perennial vegetation with a density of at least 70% of the native background cover on unpaved areas.

Does temporary stabilization count to close a site?

No. A small site must reach final stabilization before it removes its notice.

Who has to stabilize a lot sold to a buyer?

The homebuilder finishes it, or sets temporary stabilization before the transfer and tells the buyer why final stabilization is needed.

Facts and sources